Project overview
Scope of works
- Soft strip
- Demolition
- Extensive temporary works to superstructure
- New roof with dormer window
- Piling
- Excavation to 5m
- Single story basement at 150 sq/m
- Cavity drain membrane system
- Brickwork for erection of new house
- Specialist masonry and pointing works
Client:
Private Client
Structural Engineer:
MMP Design
Architect:
BDS & Maria Group
Duration:
25 weeks
Size:
150 sq/m
Project Type:
Structures, fit-out