The rebuild of 5 new luxury townhouses in the prestigious area of Knightsbridge.
Project overview
Scope of works
- Piling works
- Installation of a ground source heat pump
- Excavation and formation of a double basement with plantroom
- Formation of superstructure and complete façade works to 5 new townhouses
Client:
CCLP Ltd.
Architect:
Stanesby
Structural Engineer:
Axiom
Duration:
64 weeks
Size:
Overall – 2150 sq/m
Basement – 910 sq/m
Project Type:
Construction, Structure, Basement
Share:


Luxury London Townhouses
The scheme, of which sits within the Knightsbridge Conservation Area, close to Trevor Square, includes the demolition of 6 existing houses that date back to the 1960’s, and replacing them with 5 luxury townhouses.
Knowles’ scope of work includes the excavation of a complete footprint basement, build of a 3-storey superstructure and complete shell & core works including envelope works.
Phase 2, upon appointment, will include the final fit-out and finishes.
Each luxury townhouse will be 3,500 sq/ft and aid in revitalisation of the Brompton Road’s surrounding streets. With commencement beginning in January, phase 1 will be complete in April 2023, with full scheme completion expected in November 2023.


“Super-prime construction firm Knowles, has been picked as Principal Contractor to deliver Phase 1 works at 3-11 Lancelot Place, in Knightsbridge’s Trevor Square Conservation Area… One of the world’s most iconic locations!”
Prime Resi



“The proposal represents a successful re-interpretation of the London terrace for the 21st century… it will contribute more positively overall to the character of the area.”
Westminster City Council